# GoodGo Platform AI — Implementation Plan
|
||||
|
||||
**Last Updated:** 2026-04-09
|
||||
**Last Updated:** 2026-04-10
|
||||
|
||||
---
|
||||
|
||||
@@ -200,17 +200,110 @@ TEC-1599..1604 (P2 quality) ── (all independent, parallel)
|
||||
| TEC-1603 | None |
|
||||
| TEC-1604 | None |
|
||||
|
||||
### Milestone 8: Post-MVP Improvements (Phase 7)
|
||||
|
||||
**Goal:** Fix remaining bugs, harden for production, improve UX and DX.
|
||||
|
||||
**Wave 1 — Critical Bug Fixes (1-2 days):**
|
||||
1. **[TEC-1647] Fix Reviews routing** (P0, no deps)
|
||||
2. **[TEC-1648] Fix Health endpoints** (P0, no deps)
|
||||
3. **[TEC-1649] Fix Login error handling** (P0, needs DB)
|
||||
4. **[TEC-1650] Fix Listing 404** (P1, needs DB)
|
||||
|
||||
**Wave 2 — Production Readiness (3-5 days):**
|
||||
5. **[TEC-1651] E2E CI environment** (P1, no deps)
|
||||
6. **[TEC-1652] Run E2E tests** (P1, after Wave 1 fixes)
|
||||
7. **[TEC-1653] Security headers audit** (P1, no deps)
|
||||
8. **[TEC-1658] PgBouncer pooling** (P1, no deps)
|
||||
|
||||
**Wave 3 — User-Facing Quality (1-2 weeks):**
|
||||
9. **[TEC-1654] Mobile responsive** (P1, no deps)
|
||||
10. **[TEC-1655] SEO optimization** (P1, no deps)
|
||||
11. **[TEC-1656] Per-user rate limiting** (P1, no deps)
|
||||
12. **[TEC-1657] Admin audit logging** (P1, no deps)
|
||||
|
||||
**Wave 4 — Engineering Excellence (2-3 weeks):**
|
||||
13. **[TEC-1659] Graceful degradation** (P2, no deps)
|
||||
14. **[TEC-1660] Error codes documentation** (P2, no deps)
|
||||
15. **[TEC-1661] RUM + Web Vitals** (P2, no deps)
|
||||
16. **[TEC-1662] Update QA Tracker** (P2, after Wave 2)
|
||||
|
||||
```
|
||||
TEC-1647 (Reviews) ──┐
|
||||
TEC-1648 (Health) ────┼── TEC-1652 (E2E Tests) ── TEC-1662 (QA Update)
|
||||
TEC-1649 (Login) ─────┤
|
||||
TEC-1650 (Listing) ───┘
|
||||
TEC-1651 (CI E2E) ──────── (independent)
|
||||
TEC-1653 (Headers) ─────── (independent)
|
||||
TEC-1658 (PgBouncer) ───── (independent)
|
||||
TEC-1654..1657 (Wave 3) ── (all independent, parallel)
|
||||
TEC-1659..1661 (Wave 4) ── (all independent, parallel)
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Dependency Map (Phase 7)
|
||||
|
||||
| Task | Depends On |
|
||||
| --------------- | ----------------- |
|
||||
| TEC-1647 | None |
|
||||
| TEC-1648 | None |
|
||||
| TEC-1649 | None |
|
||||
| TEC-1650 | None |
|
||||
| TEC-1651 | None |
|
||||
| TEC-1652 | TEC-1647, TEC-1648 |
|
||||
| TEC-1653 | None |
|
||||
| TEC-1654 | None |
|
||||
| TEC-1655 | None |
|
||||
| TEC-1656 | None |
|
||||
| TEC-1657 | None |
|
||||
| TEC-1658 | None |
|
||||
| TEC-1659 | None |
|
||||
| TEC-1660 | None |
|
||||
| TEC-1661 | None |
|
||||
| TEC-1662 | TEC-1652 |
|
||||
|
||||
### Milestone 9: CEO Audit Wave 5 — Security & Features (Phase 7 continued)
|
||||
|
||||
**Goal:** Address security vulnerabilities, improve test coverage, implement missing Sprint 3 feature.
|
||||
|
||||
**Wave 5a — Security (DAY 1-2, parallel):**
|
||||
1. **[TEC-1684] Fix npm vulnerabilities** (P0, Security Engineer)
|
||||
2. **[TEC-1685] Fix lint error** (P1, QA Engineer)
|
||||
|
||||
**Wave 5b — Quality & Features (WEEK 1-2):**
|
||||
3. **[TEC-1686] Test coverage push** (P1, QA Engineer, after 5a)
|
||||
4. **[TEC-1688] Saved Searches + Alerts** (P1, Architect)
|
||||
5. **[TEC-1687] Dependabot setup** (P2, DevOps Engineer)
|
||||
|
||||
```
|
||||
TEC-1684 (NPM Vuln) ─────── (independent, P0)
|
||||
TEC-1685 (Lint) ──────────── TEC-1686 (Test Coverage)
|
||||
TEC-1688 (Saved Searches) ── (independent, P1)
|
||||
TEC-1687 (Dependabot) ────── (independent, P2)
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Dependency Map (Wave 5)
|
||||
|
||||
| Task | Depends On |
|
||||
| --------------- | ----------------- |
|
||||
| TEC-1684 | None |
|
||||
| TEC-1685 | None |
|
||||
| TEC-1686 | TEC-1685 |
|
||||
| TEC-1687 | None |
|
||||
| TEC-1688 | None |
|
||||
|
||||
---
|
||||
|
||||
## Rollout Notes
|
||||
|
||||
- **Phase 0-3 complete** — 23/23 tasks done
|
||||
- **Phase 4 is immediate priority** — security fixes must land before any production deployment
|
||||
- **Phase 6 Sprint 1 can run in parallel with Phase 4** — TEC-1592, 1593, 1594 are independent
|
||||
- **TEC-1449 (JWT) is the single most critical fix** — blocks production deployment
|
||||
- **TEC-1592 (Commit untracked files) blocks Agent Portal + AI + Payments** — do first
|
||||
- **Security tasks (TEC-1449, 1451, 1452, 1453) can all run in parallel** — assign to Security Engineer + Senior Backend
|
||||
- **TEC-1450 (Deployment Pipeline) should start after security fixes** — no point deploying insecure code
|
||||
- **Phase 5 and Phase 6 P2 tasks are all independent** — can run fully in parallel
|
||||
- **Critical path:** TEC-1449 → TEC-1450 → TEC-1457 (security → deploy → observability)
|
||||
- **Feature path:** TEC-1592 → TEC-1595/1596/1597 (commit → features)
|
||||
- **Phase 0-6 complete** — 51/51 tasks done, MVP feature-complete
|
||||
- **Phase 7 is current priority** — bug fixes and production hardening
|
||||
- **Wave 1 is immediate** — 4 critical bug fixes, low effort, high impact
|
||||
- **Wave 1 tasks can run in parallel** — no dependencies between them
|
||||
- **TEC-1652 (E2E) depends on Wave 1** — bugs must be fixed before E2E verification
|
||||
- **Wave 3-4 tasks are all independent** — can run fully in parallel
|
||||
- **Critical path:** TEC-1647/1648/1649 → TEC-1652 → TEC-1662 (bug fixes → E2E → QA update)
|
||||
- **Production path:** Wave 1 → Wave 2 → go-live decision
|
||||
|
||||