docs: add project documentation — changelog, QA tracker, audit reports, and guides
Add comprehensive project documentation including changelog, QA tracker, code quality audit, implementation guide, K6 load testing guide, frontend exploration notes, and file mapping reference. Co-Authored-By: Paperclip <noreply@paperclip.ing>
This commit is contained in:
@@ -1,6 +1,6 @@
|
||||
# GoodGo Platform AI — Implementation Plan
|
||||
|
||||
**Last Updated:** 2026-04-08
|
||||
**Last Updated:** 2026-04-09
|
||||
|
||||
---
|
||||
|
||||
@@ -145,15 +145,72 @@ Phase 4 done ──→ TEC-1458 (Redis Caching)
|
||||
| TEC-1460 | None |
|
||||
| TEC-1461 | None |
|
||||
|
||||
### Milestone 7: MVP Feature Completion & Audit (Phase 6)
|
||||
|
||||
**Goal:** Complete remaining MVP features (Agent Portal, AI, Payments), clean up tech debt from audit.
|
||||
|
||||
**Sprint 1 — Stabilize (Week 1):**
|
||||
1. **[TEC-1592] Commit untracked files** (P0, no deps)
|
||||
2. **[TEC-1593] Fix Architect agent** (P0, no deps)
|
||||
3. **[TEC-1594] i18n consolidation** (P1, no deps)
|
||||
|
||||
**Sprint 2 — Agent Portal + Payments (Weeks 2-3):**
|
||||
4. **[TEC-1595] Agent Portal** (P1, after TEC-1592)
|
||||
5. **[TEC-1597] Payment flow** (P1, after TEC-1592)
|
||||
6. **[TEC-1598] Smoke tests** (P1, independent)
|
||||
|
||||
**Sprint 3 — AI & Quality (Weeks 4-5):**
|
||||
7. **[TEC-1596] AI/ML integration** (P1, after TEC-1592)
|
||||
8. **[TEC-1599] Test coverage** (P2, independent)
|
||||
9. **[TEC-1600] OpenAPI docs** (P2, independent)
|
||||
|
||||
**Sprint 4 — Hardening (Weeks 5-6):**
|
||||
10. **[TEC-1601] K6 baselines** (P2, independent)
|
||||
11. **[TEC-1602] Security audit** (P2, after Phase 4 security fixes)
|
||||
12. **[TEC-1603] DB index optimization** (P2, independent)
|
||||
13. **[TEC-1604] Sentry integration** (P2, independent)
|
||||
|
||||
```
|
||||
TEC-1592 (Commit) ──┬── TEC-1595 (Agent Portal)
|
||||
├── TEC-1596 (AI/ML)
|
||||
└── TEC-1597 (Payments)
|
||||
TEC-1593 (Architect Fix) ─── (independent)
|
||||
TEC-1594 (i18n) ────────────── (independent)
|
||||
TEC-1598 (Smoke Tests) ─────── (independent)
|
||||
TEC-1599..1604 (P2 quality) ── (all independent, parallel)
|
||||
```
|
||||
|
||||
---
|
||||
|
||||
## Dependency Map (Phase 6)
|
||||
|
||||
| Task | Depends On |
|
||||
| --------------- | ----------------- |
|
||||
| TEC-1592 | None |
|
||||
| TEC-1593 | None |
|
||||
| TEC-1594 | None |
|
||||
| TEC-1595 | TEC-1592 |
|
||||
| TEC-1596 | TEC-1592 |
|
||||
| TEC-1597 | TEC-1592 |
|
||||
| TEC-1598 | None |
|
||||
| TEC-1599 | None |
|
||||
| TEC-1600 | None |
|
||||
| TEC-1601 | None |
|
||||
| TEC-1602 | Phase 4 security |
|
||||
| TEC-1603 | None |
|
||||
| TEC-1604 | None |
|
||||
|
||||
---
|
||||
|
||||
## Rollout Notes
|
||||
|
||||
- **Phase 0-3 complete** — 23/23 tasks done
|
||||
- **Phase 4 is immediate priority** — security fixes must land before any production deployment
|
||||
- **Phase 6 Sprint 1 can run in parallel with Phase 4** — TEC-1592, 1593, 1594 are independent
|
||||
- **TEC-1449 (JWT) is the single most critical fix** — blocks production deployment
|
||||
- **TEC-1592 (Commit untracked files) blocks Agent Portal + AI + Payments** — do first
|
||||
- **Security tasks (TEC-1449, 1451, 1452, 1453) can all run in parallel** — assign to Security Engineer + Senior Backend
|
||||
- **TEC-1450 (Deployment Pipeline) should start after security fixes** — no point deploying insecure code
|
||||
- **TEC-1456 (Tests) and TEC-1455 (DB Index) are independent** — can run anytime
|
||||
- **Phase 5 tasks are all independent** — can run fully in parallel once Phase 4 is done
|
||||
- **Phase 5 and Phase 6 P2 tasks are all independent** — can run fully in parallel
|
||||
- **Critical path:** TEC-1449 → TEC-1450 → TEC-1457 (security → deploy → observability)
|
||||
- **Feature path:** TEC-1592 → TEC-1595/1596/1597 (commit → features)
|
||||
|
||||