GoodGo Platform AI — Implementation Plan
Last Updated: 2026-04-09
Milestones
Milestone 1: Walking Skeleton (Phase 0)
Goal: Any engineer can clone, install, and start developing.
Execution Order:
- [TEC-1415] Monorepo Scaffolding + [TEC-1416] Docker Compose (parallel — no deps)
- [TEC-1420] ESLint/Prettier (after F1)
- [TEC-1417] Prisma Schema (after F1 + F2)
- [TEC-1418] Shared Module (after F1)
- [TEC-1419] CI/CD Pipeline (after F1)
F1 (Monorepo) ──┬── F6 (Lint/Prettier)
├── F3 (Prisma Schema) ←── F2 (Docker)
├── F4 (Shared Module)
└── F5 (CI/CD)
F2 (Docker) ─────┘
Milestone 2: Core Product (Phase 1)
Goal: Users can register, post listings, and search properties.
Execution Order:
- [TEC-1421] Auth Backend (after F3, F4)
- [TEC-1425] Security Hardening + [TEC-1426] Error Handling (parallel, after F1/F4)
- [TEC-1422] Auth Frontend (after C1)
- [TEC-1423] Listings Backend (after C1)
- [TEC-1424] Search Backend (after C3)
- [TEC-1427] Listings Frontend (after C3)
- [TEC-1428] Search + Landing Frontend (after C5)
F3 + F4 ──→ C1 (Auth BE) ──┬── C2 (Auth FE)
├── C3 (Listings BE) ──┬── C5 (Search BE) ──→ C6 (Search FE)
│ └── C4 (Listings FE)
├── X1 (Security)
└── X3 (Error Handling)
Milestone 3: Monetization (Phase 2)
Goal: Revenue-generating MVP with payments, subscriptions, and admin tools.
C1 ──→ M1 (Payments) ──→ M2 (Subscriptions)
C1 ──→ M3 (Notifications)
C1 + C3 ──→ M4 (Admin)
Phase 1 ──→ X4 (E2E Tests)
Milestone 4: AI-Powered (Phase 3)
Goal: Differentiated product with AI features.
F2 ──→ A1 (AI/ML Container) ──→ A2 (Analytics)
C5 + A2 ──→ A3 (MCP Servers)
Dependency Map
| Task | Depends On |
|---|---|
| TEC-1415 (F1) | None |
| TEC-1416 (F2) | None |
| TEC-1417 (F3) | F1, F2 |
| TEC-1418 (F4) | F1 |
| TEC-1419 (F5) | F1 |
| TEC-1420 (F6) | F1 |
| TEC-1421 (C1) | F3, F4 |
| TEC-1422 (C2) | C1 |
| TEC-1423 (C3) | C1, F3 |
| TEC-1424 (C5) | C3, F2 |
| TEC-1425 (X1) | F1 |
| TEC-1426 (X3) | F4 |
| TEC-1427 (C4) | C3 |
| TEC-1428 (C6) | C5 |
| TEC-1429 (M1) | C1 |
| TEC-1430 (M2) | M1 |
| TEC-1431 (M3) | C1 |
| TEC-1432 (M4) | C1, C3 |
| TEC-1433 (X4) | Phase 1 |
Milestone 5: Production Hardening (Phase 4)
Goal: Fix all critical security issues. Establish production deployment capability.
Execution Order:
- [TEC-1449] JWT Secret Fix + [TEC-1451] HMAC Timing Fix + [TEC-1452] MinIO Fix + [TEC-1453] CSRF (parallel — no deps between them)
- [TEC-1455] DB Index (independent — can run parallel with above)
- [TEC-1450] Deployment Pipeline (after security fixes verified)
- [TEC-1457] Backups + Logs (after deployment infra exists)
- [TEC-1456] Test Coverage (parallel — independent of infra)
TEC-1449 (JWT) ──────┐
TEC-1451 (HMAC) ─────┤
TEC-1452 (MinIO) ────┼──→ TEC-1450 (Deploy Pipeline) ──→ TEC-1457 (Backups + Logs)
TEC-1453 (CSRF) ─────┘
TEC-1455 (DB Index) ──────────────────────────────────(independent)
TEC-1456 (Tests) ─────────────────────────────────────(independent)
Milestone 6: Quality & Polish (Phase 5)
Goal: Production-quality UX, documentation, and performance.
Phase 4 done ──→ TEC-1458 (Redis Caching)
TEC-1459 (Frontend Polish) (parallel)
TEC-1460 (OpenAPI/Swagger) (parallel)
TEC-1461 (Documentation) (parallel)
Dependency Map (Phase 4-5)
| Task | Depends On |
|---|---|
| TEC-1449 | None |
| TEC-1450 | TEC-1449 (security first) |
| TEC-1451 | None |
| TEC-1452 | None |
| TEC-1453 | None |
| TEC-1455 | None |
| TEC-1456 | None |
| TEC-1457 | TEC-1450 |
| TEC-1458 | Phase 4 |
| TEC-1459 | None |
| TEC-1460 | None |
| TEC-1461 | None |
Milestone 7: MVP Feature Completion & Audit (Phase 6)
Goal: Complete remaining MVP features (Agent Portal, AI, Payments), clean up tech debt from audit.
Sprint 1 — Stabilize (Week 1):
- [TEC-1592] Commit untracked files (P0, no deps)
- [TEC-1593] Fix Architect agent (P0, no deps)
- [TEC-1594] i18n consolidation (P1, no deps)
Sprint 2 — Agent Portal + Payments (Weeks 2-3): 4. [TEC-1595] Agent Portal (P1, after TEC-1592) 5. [TEC-1597] Payment flow (P1, after TEC-1592) 6. [TEC-1598] Smoke tests (P1, independent)
Sprint 3 — AI & Quality (Weeks 4-5): 7. [TEC-1596] AI/ML integration (P1, after TEC-1592) 8. [TEC-1599] Test coverage (P2, independent) 9. [TEC-1600] OpenAPI docs (P2, independent)
Sprint 4 — Hardening (Weeks 5-6): 10. [TEC-1601] K6 baselines (P2, independent) 11. [TEC-1602] Security audit (P2, after Phase 4 security fixes) 12. [TEC-1603] DB index optimization (P2, independent) 13. [TEC-1604] Sentry integration (P2, independent)
TEC-1592 (Commit) ──┬── TEC-1595 (Agent Portal)
├── TEC-1596 (AI/ML)
└── TEC-1597 (Payments)
TEC-1593 (Architect Fix) ─── (independent)
TEC-1594 (i18n) ────────────── (independent)
TEC-1598 (Smoke Tests) ─────── (independent)
TEC-1599..1604 (P2 quality) ── (all independent, parallel)
Dependency Map (Phase 6)
| Task | Depends On |
|---|---|
| TEC-1592 | None |
| TEC-1593 | None |
| TEC-1594 | None |
| TEC-1595 | TEC-1592 |
| TEC-1596 | TEC-1592 |
| TEC-1597 | TEC-1592 |
| TEC-1598 | None |
| TEC-1599 | None |
| TEC-1600 | None |
| TEC-1601 | None |
| TEC-1602 | Phase 4 security |
| TEC-1603 | None |
| TEC-1604 | None |
Rollout Notes
- Phase 0-3 complete — 23/23 tasks done
- Phase 4 is immediate priority — security fixes must land before any production deployment
- Phase 6 Sprint 1 can run in parallel with Phase 4 — TEC-1592, 1593, 1594 are independent
- TEC-1449 (JWT) is the single most critical fix — blocks production deployment
- TEC-1592 (Commit untracked files) blocks Agent Portal + AI + Payments — do first
- Security tasks (TEC-1449, 1451, 1452, 1453) can all run in parallel — assign to Security Engineer + Senior Backend
- TEC-1450 (Deployment Pipeline) should start after security fixes — no point deploying insecure code
- Phase 5 and Phase 6 P2 tasks are all independent — can run fully in parallel
- Critical path: TEC-1449 → TEC-1450 → TEC-1457 (security → deploy → observability)
- Feature path: TEC-1592 → TEC-1595/1596/1597 (commit → features)